Bombay High Court Upholds Interim Arbitral Award; Holds Ready Reckoner Rate Is Minimum Compensation Under LARR Act
Facts
The dispute concerned land situated at Majiwada, Thane, originally owned by Late Dinshaw Cawasji Doongriwalla, a portion of which was acquired by the Municipal Corporation of Greater Mumbai (MCGM) in 1951 for construction of the Tansa Lake pipeline protective wall and allied structures. Although an acquisition award was passed in 1951, disputes regarding the correct market value and compensation continued for decades.
In earlier proceedings, the Bombay High Court held that compensation had to be determined under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (LARR Act) instead of the Land Acquisition Act, 1894, and appointed a Sole Arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to determine the compensation.
During arbitration, MCGM filed its Statement of Defence stating that the applicable Ready Reckoner rate for the acquired property was ₹28,500 per sq. metre and annexed a detailed calculation sheet. Treating this statement as a clear admission, the Sole Arbitrator passed an interim award under Section 31(6) directing MCGM to pay ₹14,15,90,119, together with statutory benefits under the LARR Act. MCGM challenged the interim award under Section 34 of the Arbitration Act.
Issues
- Whether the Sole Arbitrator could pass an interim award under Section 31(6) without any formal application from the claimants.
- Whether MCGM’s Statement of Defence contained a clear judicial admission regarding the applicable Ready Reckoner rate.
- Whether the Arbitrator rightly treated the admitted Ready Reckoner value as the minimum market value under Section 26 of the LARR Act, 2013.
- Whether grant of solatium and statutory interest on the interim compensation was legally permissible.
- Whether the interim award suffered from patent illegality or perversity warranting interference under Section 34 of the Arbitration Act.
Petitioner’s Arguments
MCGM contended that the interim award was patently illegal because no application seeking an interim award had been filed and the Arbitrator passed the award suo motu when the matter was fixed for final arguments.
It argued that the Statement of Defence merely corrected the claimants’ erroneous reliance on a Ready Reckoner rate of ₹35,500 per sq. metre and did not amount to an unequivocal admission that ₹28,500 represented the market value for compensation purposes.
MCGM further submitted that a decree or award based on admission can be passed only where the admission is clear, unconditional and unequivocal, relying upon decisions including Vikrant Kapila v. Pankaja Panda and Pushpa v. Dayawati.
It was also argued that solatium and statutory interest could not be awarded on an interim determination of compensation and that Section 31(6) did not permit passing such an interim award without determination of specific issues.
Respondents’ Arguments
The respondents argued that Section 31(6) expressly empowers an arbitral tribunal to pass an interim award “at any time” and “on any matter” capable of final determination, making a separate application unnecessary.
They contended that MCGM had unequivocally admitted in its pleadings that:
- the acquired land fell within Zone 6/26;
- the applicable Ready Reckoner rate was ₹28,500 per sq. metre; and
- the Corporation itself had prepared a calculation sheet based upon that rate.
According to the respondents, these constituted judicial admissions, enabling the Arbitrator to determine at least the minimum compensation payable under Section 26 of the LARR Act.
They further submitted that statutory benefits such as solatium and interest automatically follow determination of compensation under the LARR Act and were therefore rightly awarded.
Analysis of the Law
The High Court analysed the scope of Section 31(6) of the Arbitration and Conciliation Act, 1996, observing that an arbitral tribunal may pass an interim award at any stage and on any matter which it is competent to finally determine.
Relying on Indian Farmers Fertilizer Cooperative Ltd. v. Bhadra Products, the Court held that the expression “any matter” has wide amplitude and is not confined to formally framed issues. If a dispute finally determinable by the tribunal contains an admitted component, that aspect may legitimately be decided through an interim award.
The Court also examined Order XII Rule 6 CPC and reiterated that judgments on admission may be passed either on application or suo motu, provided the admission is clear, categorical, unconditional and unequivocal. Judicial admissions made in pleadings occupy a particularly high evidentiary status and dispense with proof.
Turning to Section 26 of the LARR Act, the Court held that the Collector or Arbitrator must adopt the highest of the three prescribed valuation methods. Consequently, where the applicable Ready Reckoner value is admitted, compensation cannot fall below that statutory minimum.
Precedent Analysis
The Court relied upon several leading authorities:
- Indian Farmers Fertilizer Cooperative Ltd. v. Bhadra Products—holding that interim awards may decide any matter capable of final adjudication.
- Palmview Investments Overseas Ltd. v. Ravi Arya—recognising the wide ambit of interim arbitral awards.
- Uttam Singh Duggal & Co. Ltd. v. United Bank of India, Karam Kapahi v. Lal Chand Public Charitable Trust, and Rajiv Ghosh v. Satyanarayan Jaiswal—explaining the object and scope of judgments on admission under Order XII Rule 6 CPC.
- Vikrant Kapila v. Pankaja Panda and Pushpa v. Dayawati—reaffirming that only clear, unequivocal and unconditional admissions justify judgment on admission.
- MMTC Ltd. v. Vedanta Ltd., Ssangyong Engineering v. NHAI, McDermott International, and Dyna Technologies—setting out the limited scope of interference under Section 34 of the Arbitration Act.
Court’s Reasoning
Justice N.J. Jamadar held that MCGM’s pleadings went far beyond merely disputing the claimants’ valuation. The Corporation had specifically admitted that:
- the acquired property fell in Zone 6/26;
- the applicable Ready Reckoner rate was ₹28,500 per sq. metre; and
- compensation calculations based on that rate had already been prepared.
The Court concluded that these statements constituted clear judicial admissions, which the Arbitrator rightly relied upon while passing the interim award.
The Court further held that the Arbitrator was empowered to act suo motu under Section 31(6), and neither a formal application nor prior framing of issues was a statutory prerequisite.
Rejecting the challenge to grant of solatium and statutory interest, the Court held that these benefits necessarily flow from determination of compensation under the LARR Act.
Finally, the Court emphasised that judicial review under Section 34 is extremely limited. Since the Arbitrator’s interpretation represented a plausible view based on admitted pleadings and the statutory framework, no ground of patent illegality or perversity was established. The Court also noted that the landowners had been awaiting proper compensation for nearly seventy-five years, reinforcing the equity of the interim award.
Conclusion
The Bombay High Court dismissed MCGM’s petition under Section 34 and upheld the interim arbitral award directing payment of ₹14.15 crore together with statutory benefits.
The Court held that:
- an Arbitrator may pass an interim award suo motu under Section 31(6);
- a clear admission in pleadings is sufficient to support such an award;
- the admitted Ready Reckoner rate constituted the statutory minimum market value under Section 26 of the LARR Act; and
- no patent illegality or perversity warranted interference under Section 34 of the Arbitration and Conciliation Act.
Case Details
Case: Municipal Corporation of Greater Mumbai v. Kekobad Dossabhoy Doongriwalla & Anr.
Court: High Court of Judicature at Bombay, Ordinary Original Civil Jurisdiction
Case Number: Commercial Arbitration Petition No. 543 of 2025
Judge: Hon’ble Mr. Justice N. J. Jamadar
Date: 29 July 2026
Result: Petition Dismissed with Costs. The Bombay High Court upheld the interim arbitral award granting compensation based on MCGM’s admitted Ready Reckoner rate and refused to interfere under Section 34 of the Arbitration and Conciliation Act.