Site icon Raw Law

Construction Work Cannot Be Continued Through Third Party Until Contractual Post-Termination Period Ends: Madras High Court

Employer Cannot Hand Over Terminated Construction Work to Third Party Before Contractual 30-Day Handover Period Expires

The Madras High Court has held that an employer cannot immediately take over and continue terminated construction work through another contractor when the original contractor is still within the contractually permitted period for completing its post-termination obligations.

Justice K. Kumaresh Babu restrained Yuzhan Technology India Private Limited from continuing the disputed works, either by itself or through third parties, until 29 June 2026. The Court found that the 30-day period granted to BNR Infrastructure Projects Private Limited for handing over materials, documents and project records had not yet expired.

The Court, however, left the wider disputes concerning responsibility for delay, validity of the partial termination and invocation of bank guarantees to be decided in arbitration.

Facts

Yuzhan Technology India Private Limited awarded construction work to BNR Infrastructure Projects Private Limited. The parties entered into an agreement dated 29 October 2025.

BNR subsequently entered into sub-contract arrangements with third parties for portions of the project.

Disputes arose concerning delay in the execution of the works. BNR alleged that Yuzhan had delayed handing over the site and finalising the project designs. It relied upon a report prepared by Cushman and Wakefield India Private Limited, the project coordinator appointed by Yuzhan, to contend that delays were attributable to the employer and its design agencies.

Yuzhan, on the other hand, alleged that BNR had also failed to progress the work within the agreed timeline. It claimed that the contractor had acknowledged deficiencies during stakeholder meetings and had undertaken to submit and follow a catch-up plan.

On 30 May 2026, Yuzhan issued a notice partially terminating BNR’s contract. The termination notice referred to an earlier corrective notice dated 31 March 2026 and a review meeting held on 21 April 2026.

A separate notice regarding post-termination obligations was also issued, requiring BNR to comply with Clause 18.1.3 of the agreement within 30 days.

BNR approached the Madras High Court under Section 9 of the Arbitration and Conciliation Act, 1996, seeking:

An arbitrator had already been appointed by consent of the parties.

The Court had earlier appointed an Advocate Commissioner to conduct a joint inspection and directed the parties to maintain status quo without affecting ongoing construction activities.

A dispute then arose regarding the meaning of the status quo order. BNR argued that Yuzhan and the replacement contractors could not dismantle or use BNR’s materials. Yuzhan contended that after termination it was entitled to continue the works and use materials and equipment available at the site.

Issues

The principal issues before the Court were:

  1. Whether the Court should determine at the interim stage which party was responsible for delay in the project.
  2. Whether the partial termination of BNR’s contract was prima facie invalid for failure to issue proper corrective and prior termination notices.
  3. Whether Yuzhan could immediately continue the terminated works through itself or a third-party contractor.
  4. Whether Yuzhan could use, retain or deploy BNR’s machinery, equipment and materials before completion of the contractual final-settlement process.
  5. When the employer’s right under Clause 18.1.7 to continue the terminated works became operational.
  6. Whether BNR was entitled to protection until expiry of the 30-day period granted for compliance with its post-termination obligations.
  7. Whether the disputes relating to delay, termination and contractual liability should be left to the arbitral tribunal.

Petitioner’s Arguments

BNR argued that substantial delays had occurred in handing over the site and finalising the project designs.

It relied upon the project coordinator’s report to contend that the delays were attributable to Yuzhan and its design agency.

BNR referred to Clause 3.1.5 of the agreement, which provided for an extension of time equivalent to delays attributable to the employer.

It also relied upon Clauses 4.1.2 and 4.4.2 to argue that it could not be held responsible for delays caused by the employer.

BNR contended that Clause 18.1.1 required Yuzhan to issue a written notice calling upon the contractor to rectify any breach within a reasonable period.

According to BNR, issuance of a proper notice to correct was a mandatory precondition for termination under Clause 18.1.2.

It argued that no valid corrective notice or 30-day prior termination notice had been served before the partial termination dated 30 May 2026.

BNR therefore submitted that the termination was legally and contractually defective.

It further argued that Yuzhan and the replacement contractors could not dismantle or use BNR’s materials and equipment while the dispute was pending.

BNR submitted that under Clause 18.1.3, it had 30 days from the date of the termination notice to complete its post-termination obligations, including handing over documents, completed works and project materials.

Since this period would expire only on 29 June 2026, Yuzhan could not invoke its right to continue the works before that date.

BNR sought continuation of status quo until the arbitral tribunal considered its application for interim relief under Section 17 of the Arbitration and Conciliation Act.

Respondent’s Arguments

Yuzhan argued that the project was required to be completed within the agreed timeline because statutory incentives and other benefits were linked to timely establishment of the industrial facility.

It contended that BNR was also responsible for substantial delay in progressing the works.

According to Yuzhan, BNR had accepted deficiencies during meetings conducted in November 2025 and April 2026 and had agreed to take corrective measures and submit a catch-up plan.

Yuzhan argued that Clause 18.1.1 did not require a corrective notice in every case of termination.

It submitted that some of the grounds under Clause 18.1.2, including dissipation of assets, lack of resources, insolvency and similar circumstances, could justify termination without a prior opportunity to cure.

It also relied upon Clause 20.6, which allegedly permitted termination for the employer’s convenience without assigning reasons.

Yuzhan further argued that any claim for extension of time had to be raised within seven days under Clause 16.1. Since BNR had not issued a timely notice claiming extension, it could not rely on employer-caused delay.

The respondent relied upon Clause 18.1.7 to contend that after termination it was entitled to complete the remaining work either itself or through third parties.

It also claimed a contractual lien over BNR’s machinery, equipment and materials at the site.

Yuzhan submitted that even if its use of the materials was later held to be unjustified, BNR could be compensated monetarily.

It therefore requested the Court to vacate the status quo order and permit the ongoing construction work to continue.

Analysis of the Law

The Court examined the powers available under Section 9 of the Arbitration and Conciliation Act, 1996.

Section 9 enables a court to grant interim protection before or during arbitral proceedings where preservation of property, contractual rights or the subject matter of arbitration is necessary.

The Court recognised that an arbitrator had already been appointed and that the substantive disputes would be considered in arbitration.

It therefore limited its examination to the immediate question of whether Yuzhan could continue the terminated work and use BNR’s materials before the contractual post-termination period expired.

Responsibility for Delay

The Court noted that both parties had made allegations concerning delay.

The project coordinator’s report prima facie indicated that there had been delay in handing over the site and finalising designs.

However, whether those delays excused BNR’s own failure to progress the works required examination of evidence.

The Court therefore declined to make any conclusive finding on responsibility for delay.

Validity of Termination

The Court also declined to interpret conclusively Clauses 18.1.1 and 18.1.2 governing notice to correct and termination.

Whether the termination notice complied with the agreement and whether a prior corrective notice was mandatory would form part of the arbitration.

The Court confined itself to examining the consequences flowing from the termination notice already issued.

Post-Termination Obligations Under Clause 18.1.3

Clause 18.1.3 required the contractor, within 30 days of receiving the termination notice or within another agreed period, to:

The termination notice was issued on 30 May 2026.

The 30-day period under Clause 18.1.3 would therefore expire on 29 June 2026.

The Court held that BNR remained entitled to use the full contractual period for carrying out its post-termination obligations.

Employer’s Lien Under Clause 18.1.5

Clause 18.1.5 provided for application of security instruments and permitted the employer to retain contractor equipment or materials where receivables remained unresolved after adjustment of available securities.

The Court held that such a lien could arise only after completion of the final-settlement process and issuance of the final-settlement certificate.

In the present case:

Yuzhan could therefore not immediately claim an operative lien over BNR’s equipment or materials.

Employer’s Right to Continue Work Under Clause 18.1.7

Clause 18.1.7 permitted the employer, after termination, to complete the balance work either itself or through third parties.

It also permitted use of:

The Court held that these rights could operate only after the contractor had been given the time contemplated under Clause 18.1.3 to complete the handover.

Since the 30-day period had not expired, the preconditions for invoking Clause 18.1.7 had not yet arisen.

Precedent Analysis

The order did not turn upon an extensive discussion of earlier judgments. The Court primarily interpreted the contractual provisions governing termination, handover, final settlement and continuation of work.

The following settled principles nevertheless informed the decision:

Limited Role of the Court Under Section 9

At the interim stage, the Court does not finally determine disputed questions relating to breach, delay or contractual liability.

Its role is to preserve the subject matter of arbitration and prevent irreversible prejudice until the arbitral tribunal can decide the dispute.

The Court therefore avoided conclusively deciding whether the termination was valid or which party was responsible for delay.

Contractual Rights Must Be Read Sequentially

Where a contract creates a sequence of rights and obligations, one party cannot ordinarily invoke a later-stage remedy before completion of the earlier contractual steps.

The Court applied this principle by holding that the employer’s right to continue the works under Clause 18.1.7 could not be invoked before expiry of the contractor’s 30-day handover period under Clause 18.1.3.

Employer’s Lien Depends on Final Determination

A contractual right to retain or use another party’s materials must be exercised strictly in accordance with the conditions stated in the agreement.

Since the lien under Clause 18.1.5 depended upon unresolved receivables after final settlement, it could not be asserted before that process was completed.

Substantive Disputes Belong Before the Arbitrator

Questions concerning validity of termination, entitlement to extension of time, responsibility for delay and monetary claims required evidence and contractual interpretation.

Such matters were appropriately left to the arbitrator rather than decided conclusively in proceedings for interim relief.

Court’s Reasoning

The Court found prima facie material indicating delay by Yuzhan in handing over the site and finalising designs.

However, it held that the effect of those delays upon BNR’s performance could not be decided without evidence.

The Court therefore refrained from deciding which party was responsible for the project delay.

It similarly declined to rule conclusively on whether the termination notice complied with Clauses 18.1.1 and 18.1.2.

The decisive question was whether Yuzhan’s contractual right to continue the works had already become enforceable.

The Court observed that BNR was granted 30 days from the termination notice to perform the obligations listed in Clause 18.1.3.

That period would end only on 29 June 2026.

Until then, BNR retained the contractual right to:

The Court held that Yuzhan could not rely upon Clause 18.1.7 to continue the work before the expiry of that period.

Similarly, Yuzhan’s right to retain or deploy BNR’s machinery and materials under Clause 18.1.5 would arise only after completion of the final-settlement process and determination of unresolved receivables.

That stage had not been reached.

The Court therefore concluded that Yuzhan could not undertake the terminated works, either directly or through another contractor, until 29 June 2026.

The order preserved the position only for the contractual handover period and did not determine the merits of the termination dispute.

The parties were granted liberty to seek further relief before the arbitrator in accordance with the earlier order dated 11 June 2026.

Conclusion

The Madras High Court disposed of the applications with a limited interim protection in favour of BNR Infrastructure Projects Private Limited.

The Court held that:

The applications were disposed of without costs.


Case: BNR Infrastructure Projects Private Limited v. Yuzhan Technology India Private Limited & Ors.
Court: High Court of Judicature at Madras
Case Number: O.A. No. 542 of 2026, A. No. 2465 of 2026 and Arbitration Application No. 1072 of 2026
Judge: Justice K. Kumaresh Babu
Date: 22 June 2026
Result: Applications disposed of; Yuzhan Technology restrained from continuing the terminated construction work, either directly or through third parties, until expiry of BNR’s contractual 30-day post-termination period on 29 June 2026, with substantive disputes left for arbitration.

Read Also: Borrower Cannot Use Pending NCLAT Appeal to Stall Bank’s Debt Transfer After OTS Rejection: Madras High Court

Exit mobile version