Site icon Raw Law

Delhi High Court Holds Arbitral Award Claim Extinguished After CIRP Resolution Plan; Directs Refund of Deposit as Creditor Failed to Lodge Claim Before Resolution Professional

Arbitral Award Holder Loses Right After Missing CIRP Claim Deadline; Delhi High Court Orders Refund of Deposited Amount

Facts

Bharat Heavy Electricals Limited (BHEL) invited bids for supplying two barrel-type blender reclaimers. McNally Bharat Engineering Company Limited (MBECL) entered into an agreement with Metso India Pvt. Ltd., under which Metso would provide technical support and later execute the subcontract if MBECL secured the project. MBECL was awarded the contract and executed a subcontract with Metso in July 2011.

Disputes arose between the parties, leading MBECL to terminate the agreement in November 2011. Metso invoked arbitration, resulting in an arbitral award directing MBECL to pay approximately ₹5.52 crore along with post-award interest. MBECL challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 and deposited the awarded amount pursuant to a stay order of the Delhi High Court.

During the pendency of the Section 34 proceedings, MBECL entered Corporate Insolvency Resolution Process (CIRP). A Resolution Plan was subsequently approved by the National Company Law Tribunal. Metso did not submit its arbitral award claim before the Resolution Professional during the CIRP. MBECL thereafter sought dismissal of the Section 34 petition as infructuous and requested refund of the amount deposited before the Court.


Issues

  1. Whether the arbitral award holder’s claim survives after approval of the Resolution Plan when the creditor failed to lodge its claim before the Resolution Professional.
  2. Whether the Section 34 petition challenging the arbitral award becomes infructuous after approval of the Resolution Plan.
  3. Whether the amount deposited before the High Court during the pendency of the Section 34 petition should be refunded to the corporate debtor or released to the award holder.

Petitioner’s Arguments

The petitioner contended that:


Respondent’s Arguments

The respondent argued that:


Analysis of the Law

The Court examined:

The Court observed that every creditor, including an arbitral award holder, must submit its claim before the Resolution Professional. Once the Resolution Plan receives approval, every claim not included therein stands extinguished by operation of law.

The Court further held that a deposit made pursuant to a stay order under Section 34 is merely a security deposit. Ownership of the money remains with the corporate debtor until the Court directs its release. Such deposit does not amount to unconditional payment to the decree holder merely because it is lying in Court.


Precedent Analysis

The Court relied upon:

On the issue of court deposits, the Court preferred the later Bombay High Court decisions in Siti Networks Ltd. v. Rajiv Suri, Reliance Naval & Engineering Ltd. v. Afcons Infrastructure Ltd., and Garden Silk Mills Ltd., holding that monies deposited in Court remain assets of the corporate debtor and may be refunded following CIRP.


Court’s Reasoning

The Court held that the respondent’s arbitral award constituted a “claim” under the IBC and therefore had to be submitted before the Resolution Professional.

Since the respondent failed to lodge its claim, the approved Resolution Plan extinguished that claim by operation of Section 31 of the IBC. Consequently, irrespective of the merits of the arbitral award, enforcement could no longer continue.

The Court further reasoned that the deposit made before the High Court was only intended to secure the award pending adjudication of the Section 34 petition. Such deposit never transferred ownership to the respondent and therefore remained an asset of the corporate debtor.

The Court rejected the respondent’s argument that deposit in Court amounted to payment, observing that earlier authorities concerning payment dealt with entitlement to interest and not ownership of the deposited money.

Accordingly, the Section 34 petition had become infructuous because the underlying claim itself had ceased to exist.


Conclusion

The Delhi High Court held that once the Resolution Plan was approved, the respondent’s arbitral award claim stood extinguished because it had not been submitted during the CIRP.

The Section 34 proceedings consequently became infructuous.

The Court directed that the entire amount deposited before the High Court, together with accrued interest, be released to McNally Bharat Engineering Company Limited.


Case Details

Case: McNally Bharat Engineering Company Limited v. Metso India Pvt. Ltd.

Court: Delhi High Court

Case Number: O.M.P. (COMM) 362/2018

Judge: Hon’ble Mr. Justice Avneesh Jhingan

Date: 03 August 2026

Result: Section 34 petition held infructuous after approval of the Resolution Plan; respondent’s arbitral claim held extinguished for failure to lodge claim during CIRP; deposited amount with accrued interest directed to be refunded to the petitioner.

Read also: Bombay High Court Upholds Immediate Sugar Export Ban; Holds Advance Payments and Private Export Contracts Do Not Override Government’s Public Interest Policy Decision

Exit mobile version