Site icon Raw Law

Supreme Court Allows Power Grid’s Appeal Against MP High Court — “High Court Ought Not to Have Entertained Writ Petitions When Appeal Under Electricity Act Was Available”

Supreme Court Allows Power Grid’s Appeal Against MP High Court — “High Court Ought Not to Have Entertained Writ Petitions When Appeal Under Electricity Act Was Available”

Supreme Court Allows Power Grid’s Appeal Against MP High Court — “High Court Ought Not to Have Entertained Writ Petitions When Appeal Under Electricity Act Was Available”

Share this article

Court’s Decision

The Supreme Court allowed the appeals filed by Power Grid Corporation of India Limited challenging the Madhya Pradesh High Court’s decision to entertain writ petitions filed by the Madhya Pradesh Power Transmission Company Limited (MPPTCL) against compensation-related orders of the Central Electricity Regulatory Commission (CERC). The Court held that:

“The CERC, while exercising its regulatory functions under Section 79(1) of the Act, 2003, can pass orders granting compensation even in the absence of specific regulations, and such orders are not beyond jurisdiction.”

It further held that:

“There exists a clear and efficacious statutory remedy of appeal under Section 111 of the Electricity Act, 2003 to the Appellate Tribunal for Electricity (APTEL), and the High Court ought not to have entertained the writ petitions.”

Accordingly, the High Court’s order admitting the writ petitions was set aside.


Facts

Power Grid Corporation (appellant) implemented transmission assets under the Western Region System Strengthening Schemes (WRSS-XIV and WRSS-XVI) at the Indore substation upon request from MPPTCL (respondent), the state transmission utility. However, MPPTCL delayed construction of downstream intra-state transmission lines, causing Power Grid to approach CERC for determination of Commercial Operation Date (COD) and approval of tariff under the 2014 Tariff Regulations.

CERC approved COD but did not condone the delay. It allowed compensation in the form of liquidated damages and incidental expenses from the newly determined COD up to the date before downstream systems were operational. MPPTCL challenged this before the High Court, arguing CERC exceeded its jurisdiction and had no power under the regulations to grant such compensation.


Issues

  1. Whether the CERC’s grant of compensation for delays was beyond its jurisdiction under the Electricity Act, 2003.
  2. Whether the High Court was justified in entertaining writ petitions despite the availability of an appellate remedy under Section 111 of the Act.
  3. Whether such compensation falls under regulatory or adjudicatory functions of CERC under Section 79.
  4. Whether the orders of CERC breached principles of natural justice or constitutional parameters warranting High Court interference.

Petitioner’s Arguments


Respondent’s Arguments


Analysis of the Law


Precedent Analysis


Court’s Reasoning


Conclusion

The Supreme Court set aside the High Court’s order admitting the writ petitions, and allowed the appeals filed by Power Grid. It held that:

“There exists a statutory mechanism of appeal under Section 111 of the Electricity Act, 2003 and no grounds existed to bypass such mechanism.”


Implications

Also Read – Delhi High Court Denies Bail in Attempt to Murder Case Noting “Dangerous Injuries” to Victim and Risk of Witness Intimidation: Holds Petitioner Actively Participated in Assault, Cannot Claim Parity with Co-Accused Released on Medical Grounds

Exit mobile version