Site icon Raw Law

Supreme Court Upholds Arbitral Award Rejecting Contractor’s Claims: Holds Clause 49.5 of GCC Validly Bars Damages for Employer-Caused Delays, Estoppel Prevents Appellant From Reneging on Written Undertakings, and Judicial Intervention Under Section 37 Arbitration Act is Limited

Supreme Court Upholds Arbitral Award Rejecting Contractor’s Claims: Holds Clause 49.5 of GCC Validly Bars Damages for Employer-Caused Delays, Estoppel Prevents Appellant From Reneging on Written Undertakings, and Judicial Intervention Under Section 37 Arbitration Act is Limited

Supreme Court Upholds Arbitral Award Rejecting Contractor’s Claims: Holds Clause 49.5 of GCC Validly Bars Damages for Employer-Caused Delays, Estoppel Prevents Appellant From Reneging on Written Undertakings, and Judicial Intervention Under Section 37 Arbitration Act is Limited

Share this article

Court’s Decision

The Supreme Court dismissed the appeal against the Delhi High Court’s decision, which upheld an arbitral award rejecting the appellant’s monetary claims. The Court ruled that Clause 49.5 of the General Conditions of Contract (GCC), which explicitly barred claims for damages arising from employer-caused delays, was legally valid and binding.

The Court emphasized that:

The Court concluded that there was no patent illegality or violation of public policy, and judicial intervention was unwarranted.


Facts of the Case


Issues Before the Court

  1. Is Clause 49.5 of the GCC enforceable, given that it bars claims for damages caused by employer delays?
  2. Did the Arbitral Tribunal err in summarily rejecting the appellant’s claims under Section 16(2) of the Arbitration Act?
  3. Is the appellant barred from claiming damages after providing a written undertaking not to seek compensation beyond escalation?
  4. Did the respondent waive Clause 49.5 through its communications?
  5. Should the Supreme Court interfere under Section 37 of the Arbitration Act?

Petitioner’s (Appellant’s) Arguments


Respondent’s Arguments


Analysis of the Law

1. Enforceability of Clause 49.5

2. Estoppel by Conduct

3. Limited Scope of Judicial Review Under Sections 34 and 37

4. Rejection of Waiver Argument


Precedents Cited

  1. Pam Developments Pvt. Ltd. v. State of West Bengal (2019) 8 SCC 112
    • Government contracts must adhere to fair commercial principles, but limitation of liability clauses are enforceable.
  2. ONGC v. Wig Brothers Builders & Engineers Pvt. Ltd. (2010) 13 SCC 377
    • Limitation of liability clauses in public contracts are valid and do not violate the Contract Act.
  3. Larsen Air Conditioning & Refrigeration Co. v. Union of India (2023) 15 SCC 472
    • Appellate intervention under Section 37 is highly restricted and cannot involve a de novo assessment of the merits.
  4. Konkan Railway Corp. Ltd. v. Chenab Bridge Project Undertaking (2023) 9 SCC 85
    • The scope of review under Section 37 is even narrower than under Section 34.

Court’s Reasoning

  1. The contract governs the claim:
    • The appellant knowingly sought extensions under Clause 49.5 and was bound by its terms.
  2. No waiver by the respondent:
    • The respondent’s letters did not waive Clause 49.5 but merely clarified that claims must be processed together with extensions.
  3. Estoppel by Conduct:
    • The appellant’s written undertakings prevented it from later challenging the clause.
  4. Limited Scope of Review:
    • The arbitral award was neither illegal nor perverse, making appellate interference impermissible.

Conclusion


Implications of the Judgment

Strengthens the enforceability of limitation of liability clauses in contracts.
Limits judicial interference in arbitration awards.
Prevents abuse of contractual extensions for financial gain.
Confirms that such clauses do not violate the Indian Contract Act.

This ruling reaffirms that contractual obligations are legally binding and must be enforced.

Also Read – Supreme Court Quashes Rape FIR Against Husband, Holds That Exception 2 to Section 375 IPC Applies in Legally Recognized Marriages and SIT Report Corroborates Voluntary Marriage

Exit mobile version