Site icon Raw Law

Bombay High Court Sets Aside ₹4.27 Crore Arbitral Award in Favour of KCPL: “Arbitrator’s findings are perverse, speculative, and lack evidentiary basis”

arbitral award
Share this article

Judgment: Board of Control for Cricket in India v. KCPL and RSW Infrastructure Limited

Date: 12 June 2024
Bench: Justice Manish Pitale, Bombay High Court


Court’s Decision

The Bombay High Court allowed the petition under Section 34 of the Arbitration and Conciliation Act, 1996, setting aside an arbitral award of ₹4.27 crores granted in favour of KCPL by the Arbitral Tribunal. The Court held that the Arbitrator had acted in patent disregard of contractual terms and had awarded damages without any evidence or justification.

“The impugned award suffers from perversity… the reasoning of the Arbitral Tribunal… cannot be sustained in the eyes of law.”


Facts

The dispute arose from a 2007 contract between the Board of Control for Cricket in India (BCCI) and KCPL for constructing the BCCI headquarters at Wankhede Stadium, Mumbai. In 2009, delays occurred, prompting BCCI to terminate the contract, alleging breach and poor performance. KCPL initiated arbitration seeking compensation for wrongful termination and damages. The Arbitral Tribunal awarded ₹4.27 crores to KCPL, prompting BCCI to file a Section 34 petition challenging the award.


Issues

  1. Whether the Arbitral Tribunal’s award was liable to be set aside under Section 34 on the grounds of perversity, non-application of mind, and lack of evidence.
  2. Whether the Tribunal had failed to appreciate documentary evidence and acted contrary to the contract.

Petitioner’s Arguments (BCCI)

BCCI argued that:


Respondent’s Arguments (KCPL)

KCPL contended that:


Analysis of the Law

The Court analyzed the reasoning of the Tribunal vis-à-vis the documentary evidence and held that:

The Court reiterated the principle that:

“Award must be based on cogent evidence and cannot be the result of mere guesswork.”


Precedent Analysis

  1. Associate Builders v. DDA (2015) 3 SCC 49
    Cited for the proposition that an arbitral award can be set aside if it is perverse or in contravention of fundamental policy of Indian law.
  2. Ssangyong Engineering v. NHAI (2019) 15 SCC 131
    Relied upon to demonstrate that awards suffering from patent illegality or ignoring contractual terms are liable to be set aside under Section 34.
  3. Delhi Airport Metro Express v. DMRC (2022) 1 SCC 131
    Emphasized that courts can interfere when arbitrators render awards ignoring contractual obligations or acting without evidence.

Court’s Reasoning

Justice Pitale found that:


Conclusion

The Bombay High Court quashed the arbitral award dated 12 September 2017, ruling it perverse and patently illegal. The petition was allowed, and no costs were awarded.


Implications

This judgment reaffirms the limited yet potent jurisdiction under Section 34, especially when arbitral awards ignore contractual terms and are unsupported by evidence. It sends a clear message that arbitral discretion cannot extend to rewriting contracts or awarding speculative damages. For public and private contracting entities, this judgment underscores the necessity of well-reasoned and evidence-based arbitration outcomes.

Also Read: Calcutta High Court Declines Interference in Port Lease Cancellation Dispute: “Doctrine of Promissory Estoppel Cannot Override Statutory Provisions of the Major Port Authorities Act”

Exit mobile version