Site icon Raw Law

Bombay High Court “section 34 is not an appellate forum to substitute one plausible commercial view with another” — arbitral award on ‘built up area wall to wall’ upheld, developer’s challenge dismissed

publishing image 63 6
Share this article

Court’s decision

The Bombay High Court dismissed the petition filed under Section 34 of the Arbitration and Conciliation Act, 1996, and refused to set aside the arbitral award arising out of a redevelopment dispute between a developer and landowners. The Court held that the arbitral tribunal’s interpretation of the contractual expression “built up area wall to wall” as referring to usable area akin to carpet area was a plausible and commercially sensible interpretation that did not warrant interference.

The Court reiterated that the jurisdiction under Section 34 is extremely limited and does not permit re-appreciation of evidence or substitution of one plausible interpretation of a commercial contract with another. It held that once the arbitral tribunal adopts a reasonable construction grounded in contractual text and commercial logic, the award must be respected. Consequently, the challenge to the arbitral award was rejected in entirety.


Court’s decision

The Court held that the arbitral tribunal had correctly rejected the developer’s attempt to proportionately reduce the landowners’ flat entitlement on the basis of an alleged shortfall in developable land area. The development agreement itself explicitly recorded the discrepancy between the actual physical area and the area reflected in the property card, and therefore the developer could not claim surprise at a later stage.

The Court also upheld the arbitral finding that the developer was not entitled to unilaterally truncate the agreed flat area and that the landowners were entitled to compensation for the shortfall in area delivered. The award was found to be reasoned, coherent, and firmly within the bounds of arbitral discretion, leaving no ground for interference under Section 34.


Facts

The dispute arose out of a development agreement executed in 2010 under which the developer undertook redevelopment of a parcel of land owned by the landowners. In consideration, the landowners were entitled to specified residential flats aggregating to 5,000 square feet of “built up area wall to wall”, along with rent for displacement and other agreed monetary components.

Construction was completed and possession was handed over in 2017. Thereafter, disputes arose regarding whether the flats handed over conformed to the contractual area entitlement. The landowners alleged a substantial shortfall in delivered area and sought monetary compensation. The developer, on the other hand, contended that the actual developable land area was lower than what was reflected in municipal records, entitling him to proportionately reduce the landowners’ flat area.


Issues

The primary issue before the High Court was whether the arbitral tribunal had committed any jurisdictional error in interpreting the contractual expression “built up area wall to wall” as meaning usable area equivalent to carpet area. A connected issue was whether the tribunal erred in rejecting the developer’s plea that the landowners’ entitlement stood proportionately reduced due to an alleged shortfall in developable land area.

The Court was also required to examine whether the arbitral award suffered from perversity, patent illegality, or exceeded the scope of the contract so as to justify interference under Section 34 of the Arbitration Act.


Petitioner’s Arguments

The developer contended that the arbitral tribunal had fundamentally misconstrued the expression “built up area wall to wall” by equating it with carpet area. It was argued that once the phrase “built up” is used, there was no scope for excluding wall thickness, and that the tribunal effectively rewrote the contract by adopting a standard not agreed upon by the parties.

The developer further argued that the arbitral tribunal ignored the impact of the discrepancy between the actual land area and the area reflected in the property card, which allegedly reduced the development potential. It was also contended that the tribunal granted relief beyond the scope of the claim by computing a higher area shortfall than what was originally pleaded.


Respondent’s Arguments

The landowners contended that the arbitral tribunal had adopted a commercially reasonable interpretation consistent with the parties’ intent. It was argued that the phrase “wall to wall” necessarily refers to usable internal area and cannot be reconciled with a purely technical concept of built-up area inclusive of wall thickness.

The landowners further submitted that the developer was fully aware of the discrepancy in land area at the time of executing the agreement, which was expressly recorded in the contractual schedule. The plea of reduced development potential, it was argued, was an afterthought raised for the first time in arbitration and rightly rejected by the tribunal.


Analysis of the law

The Court undertook a detailed examination of the scope of judicial interference under Section 34 of the Arbitration Act. It reiterated that arbitral awards are not to be treated as first appeals and that courts cannot reassess evidence or substitute their own interpretation merely because another view is possible.

The Court emphasised that interpretation of a commercial contract lies squarely within the domain of the arbitral tribunal. So long as the interpretation adopted is plausible, coherent, and grounded in contractual language and commercial sense, it cannot be interfered with. The Court also reaffirmed that Section 34 does not permit correction of mere errors of interpretation.


Precedent Analysis

The Court relied on authoritative Supreme Court precedents holding that commercial contracts must be interpreted to give them business efficacy and commercial sense. It referred to decisions emphasising that parties to commercial agreements act with open eyes and that courts must respect the contractual bargain struck between them.

The Court also relied on settled law that even if two interpretations of a contractual clause are possible, the court must not disturb the arbitral tribunal’s view if it is a reasonable one. Interference is permissible only where the award is perverse, patently illegal, or shocks the conscience of the court.


Court’s Reasoning

Applying these principles, the Court held that the arbitral tribunal’s interpretation of “built up area wall to wall” as usable area was commercially sensible and consistent with common understanding. The tribunal had not blindly imposed a statutory definition but had used regulatory definitions only as interpretative aids to discern commercial intent.

The Court further found that the developer’s plea of reduced development potential was untenable, as the agreement explicitly recorded the land area discrepancy and the developer had proceeded with full knowledge of it. The computation of the area shortfall was held to be a logical consequence of the tribunal’s interpretative finding and not an excess of jurisdiction.


Conclusion

The Bombay High Court held that the arbitral award did not suffer from perversity, patent illegality, or jurisdictional error. The challenge under Section 34 was dismissed, and the arbitral award directing compensation for shortfall in delivered flat area was upheld. The Court reiterated that arbitral autonomy and finality must be respected, particularly in commercial redevelopment disputes.


Implications

This judgment reinforces the pro-arbitration stance of Indian courts and underscores the narrow scope of interference under Section 34. It provides clarity that expressions relating to area in redevelopment agreements will be interpreted in a commercially realistic manner rather than through hyper-technical lenses. The ruling also discourages developers from reopening settled contractual bargains by invoking post-hoc pleas of reduced development potential.

Exit mobile version