Site icon Raw Law

Delhi High Court Upholds Arbitral Award: Rejects Challenge Against Liquidated Damages, Unlawful Encashment of Performance Bank Guarantee, and Misinterpretation of Price Variation Clause in Metro Rail Supply Contract Dispute

Delhi High Court Upholds Arbitral Award: Rejects Challenge Against Liquidated Damages, Unlawful Encashment of Performance Bank Guarantee, and Misinterpretation of Price Variation Clause in Metro Rail Supply Contract Dispute

Delhi High Court Upholds Arbitral Award: Rejects Challenge Against Liquidated Damages, Unlawful Encashment of Performance Bank Guarantee, and Misinterpretation of Price Variation Clause in Metro Rail Supply Contract Dispute

Share this article

Court’s Decision

The Delhi High Court dismissed a challenge to an arbitral award concerning a dispute over the supply of head-hardened rails for metro rail expansion. The court held that the arbitral tribunal correctly interpreted the contract and that judicial intervention under Section 34 of the Arbitration and Conciliation Act, 1996 was not warranted. The tribunal’s findings on liquidated damages (LD), encashment of the performance bank guarantee (PBG), and the price variation clause (PVC) were upheld, and the petition was found to be devoid of merit.


Facts


Issues

  1. Whether the arbitral tribunal correctly interpreted the contract with respect to delivery obligations and liquidated damages.
  2. Whether the petitioner was justified in encashing the Performance Bank Guarantee (PBG).
  3. Whether the respondent was entitled to price adjustments under the Price Variation Clause (PVC).
  4. Whether the arbitral tribunal erred in awarding interest despite a contractual prohibition on interest payments.
  5. Whether the arbitral tribunal properly rejected the counterclaims made by the petitioner.

Petitioner’s Arguments


Respondent’s Arguments


Analysis of the Law


Precedent Analysis

The court relied on multiple Supreme Court judgments:


Court’s Reasoning


Conclusion


Implications

Also Read – Supreme Court Upholds Arbitral Award Rejecting Contractor’s Claims: Holds Clause 49.5 of GCC Validly Bars Damages for Employer-Caused Delays, Estoppel Prevents Appellant From Reneging on Written Undertakings, and Judicial Intervention Under Section 37 Arbitration Act is Limited

Exit mobile version