Site icon Raw Law

Delhi High Court Upholds Railway Contractor’s Claim for Wrong Quantity Deductions but Sets Aside Damages and Interest Awarded Beyond Contract and Evidence Requirements

Contractor Entitled to Refund of Wrong Deductions, but Not Damages Without Proof of Loss, Rules Delhi High Court

Facts

Northern Railway invited tenders in July 2019 for doubling the Roza–Sitapur railway section. The contract, valued at over ₹42.46 crore, was awarded to M/s Pragati Construction Consultants and executed on 14 February 2020.

The contractor was required to complete the work within eight months, but owing to delays, the Railway granted six extensions and the project was ultimately completed on 15 December 2021. During execution, amendments increased the contract value.

Disputes arose regarding deductions made by the Railway, prolongation of the project, and other contractual claims. The contractor invoked arbitration seeking approximately ₹1.95 crore. The Arbitral Tribunal awarded ₹65.73 lakh with post-award interest. Aggrieved, the Union of India filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 seeking to set aside the award.


Issues

  1. Whether deductions made by the Railway from Schedule ‘A’ items were arbitrable or constituted “excepted matters” under the General Conditions of Contract (GCC).
  2. Whether the Arbitral Tribunal could award damages for prolongation of the contract without proof of actual loss.
  3. Whether the Tribunal could award damages equivalent to pendente lite interest after holding that interest itself was contractually barred.
  4. Whether only part of the arbitral award could be set aside under Section 34 of the Arbitration and Conciliation Act.

Petitioner’s Arguments

The Union of India contended that:


Respondent’s Arguments

The contractor argued that:


Analysis of the Law

The Court examined:

The Court reiterated that:


Precedent Analysis

The Court relied upon:


Court’s Reasoning

The Court upheld the Tribunal’s finding regarding wrongful deductions from Schedule ‘A’ items.

It held that the Railway had itself acted contrary to Clause 42.4(6) of the GCC by applying variation limits chapter-wise instead of to the SOR schedule as a whole. Having violated the contractual terms, the Railway could not invoke the “excepted matter” clause to avoid arbitration. The Tribunal’s interpretation was a plausible contractual interpretation warranting no interference under Section 34.

However, the Court found the award of damages for prolongation legally unsustainable. Although the delay was attributable to the Railway, the contractor had neither produced evidence of actual loss nor established that such proof was impossible. The Tribunal therefore violated Section 73 of the Contract Act by awarding damages solely on the basis of fixed cost calculations.

The Court further held that the Tribunal committed patent illegality by rejecting pendente lite interest under the contract but then awarding the identical amount as damages. This amounted to granting relief beyond the pleadings and beyond the scope of the reference.

Since Claims 4 and 6 were independent and severable from the remaining award, they could be set aside without disturbing the rest of the award.


Conclusion

The Delhi High Court partly allowed the petition.

It upheld the arbitral award directing refund of wrongful deductions relating to Schedule ‘A’ items, holding that the Railway had acted contrary to the contractual provisions and could not invoke the “excepted matter” clause.

However, the Court set aside the awards under Claim Nos. 4 and 6, holding that damages for prolongation were unsupported by evidence of actual loss and that awarding damages in place of contractually barred interest constituted patent illegality.


Case Details

Case: Union of India through Dy. Chief Engineer Construction Moradabad v. M/s Pragati Construction Consultants

Court: Delhi High Court

Case Number: O.M.P. (COMM) 153/2025

Judge: Hon’ble Mr. Justice Avneesh Jhingan

Date: 03 August 2026

Result: Petition partly allowed. Award directing refund of wrongful deductions (Claim No. 1) upheld; awards under Claim Nos. 4 and 6 set aside as patently illegal; remaining arbitral award sustained.

Read Also: Delhi High Court Holds Arbitral Award Claim Extinguished After CIRP Resolution Plan; Directs Refund of Deposit as Creditor Failed to Lodge Claim Before Resolution Professional

Exit mobile version