Site icon Raw Law

Bombay High Court Quashes Land Acquisition for Lack of Public Purpose and Non-Application of Mind: “Mere Existence of Government Scheme Does Not Justify Private Acquisition Without Due Process”

lack of public purpose
Share this article

Court’s Decision

The Bombay High Court quashed the land acquisition proceedings initiated under the Maharashtra Regional and Town Planning Act, 1966, holding that the acquisition lacked a demonstrable public purpose, violated procedural mandates, and failed to consider material objections. The Court categorically observed:

“The entire acquisition smacks of colourable exercise of power and non-application of mind… It is not a mechanical process where objections are to be brushed aside.”

Accordingly, the Court allowed the writ petition, quashed the Notification under Section 6 of the Land Acquisition Act, 1894, and the declaration of acquisition.


Facts

The petitioner owned land reserved for a public purpose (resettlement of project-affected persons) under a development plan. A notification under Section 4 of the Land Acquisition Act, 1894 was issued, followed by a declaration under Section 6. The petitioner filed objections under Section 5A, which were summarily rejected. The acquisition was allegedly made for a private beneficiary under the guise of a public project.

The core grievance of the petitioner was that the acquisition lacked bona fides, as the land was being acquired for private purposes while branding it as a public purpose. The objections raised were neither considered nor addressed in a reasoned manner by the Land Acquisition Officer or the State Government.


Issues

  1. Whether the acquisition was made for a genuine public purpose or for the benefit of a private party?
  2. Whether the rejection of the objections under Section 5A without due consideration renders the acquisition void?
  3. Whether the acquisition proceedings were vitiated due to non-application of mind and colourable exercise of power?

Petitioner’s Arguments

The petitioner argued that the acquisition was tainted with malafides and lacked public purpose. The land was being acquired not for resettlement of project-affected persons, but to serve the interest of a private society. The objections under Section 5A, which raised substantial points including availability of alternate land, misuse of planning reservation, and lack of urgency, were mechanically rejected.

The petitioner further submitted that the declaration under Section 6 was issued without proper application of mind, and in breach of the mandatory requirement to consider the petitioner’s objections. The acquisition, thus, was liable to be struck down for violating Articles 14 and 300A of the Constitution.


Respondent’s Arguments

The State contended that the acquisition was in accordance with the development plan and for a legitimate public purpose—rehabilitation of project-affected persons. It was submitted that the objections had been duly considered and rejected. The respondent emphasized that once land is reserved in the development plan, acquisition becomes necessary for implementation of the scheme.

They further argued that judicial review is limited in such matters, and the declaration under Section 6 is conclusive evidence of public purpose unless mala fides are clearly established.


Analysis of the Law

The Court analyzed the Land Acquisition Act, 1894 in conjunction with the Maharashtra Regional and Town Planning Act, 1966. It reiterated that ‘public purpose’ must be genuine, not a pretext to benefit private entities. Sections 5A and 6 were scrutinized in light of constitutional safeguards under Articles 14 and 300A.

The Court underscored that Section 5A confers a vital right on the landowner to raise objections, and these cannot be dismissed in a perfunctory or casual manner. The authorities are required to apply their mind and pass a speaking order that reflects due consideration.

It held that procedural safeguards cannot be nullified merely because a scheme exists in the development plan. The acquisition must independently pass the test of necessity, non-arbitrariness, and transparency.


Precedent Analysis

  1. Hindustan Petroleum Corporation Ltd. v. Darius Shapur Chenai (2005) 7 SCC 627
    Held that objections under Section 5A are not an empty formality; they must be considered in right earnest.
  2. Dev Sharan v. State of Uttar Pradesh (2011) 4 SCC 769
    Reiterated that acquisition must not be a colourable exercise of power or intended for private benefit.
  3. Union of India v. Shiv Raj (2014) 6 SCC 564
    Clarified that even in cases where urgency clause is not invoked, mechanical rejection of objections violates natural justice.
  4. State of Punjab v. Gurdial Singh (1980) 2 SCC 471
    Established that ‘public purpose’ must be genuine and not camouflage for private interests.

The Court found these judgments fully applicable to the present case, holding that the rejection of objections and the acquisition as a whole were arbitrary and non-transparent.


Court’s Reasoning

The High Court critically examined the manner in which the objections under Section 5A were handled. It noted that:

“The authority has failed to provide cogent reasons while rejecting the objections. There is no material to show that alternate lands were considered or that the land was indispensable.”

The Court emphasized that a mechanical endorsement of the planning authority’s proposal without an independent application of mind by the Land Acquisition Officer or the State Government defeats the very purpose of Section 5A.

Moreover, the Court held that the acquisition did not satisfy the threshold of necessity, especially since the land was being acquired years after the development plan was notified, and alternative plots were available.

The absence of a fair inquiry, reasoned order, and public purpose turned the acquisition into a colourable exercise of power.


Conclusion

The Bombay High Court allowed the writ petition, quashing the Section 6 notification and the acquisition proceedings. The land acquisition was held to be in breach of constitutional protections and statutory obligations.

“Acquisition proceedings cannot be used as a tool to aid private parties under the garb of public purpose. The process must be transparent and just.”

The Court reiterated that judicial review is available when procedural safeguards are violated and public interest is compromised.


Implications


Referred Cases and Their Relevance

FAQs

1. Can land reserved in a development plan be acquired without considering objections under Section 5A?
No. Even if land is reserved under a development plan, acquisition must follow due process, and objections under Section 5A must be fairly considered.

2. Is the declaration under Section 6 conclusive proof of public purpose?
Not always. If the declaration is challenged on grounds of mala fides, non-application of mind, or procedural violations, it is open to judicial review.

3. What happens if acquisition is done to benefit a private entity?
Such acquisition is considered a colourable exercise of power and is liable to be quashed by the court for lack of genuine public purpose.

Also Read: Supreme Court Restores Summons Under Section 319: “Duty of Court Is to Ensure Real Culprits Do Not Go Unpunished”

Exit mobile version