ganga bridge project

Patna High Court Denies Interim Protection to Land Claimants, Allows State to Continue Ganga Bridge Project, Holding “Reliefs in Land Disputes Must Await Civil Suit Adjudication; Public Projects Cannot Be Halted Indefinitely”

Share this article

Court’s Decision

The Patna High Court disposed of the Letters Patent Appeal and the connected writ petition, lifting the interim status quo and allowing the State to proceed with the construction of the six-lane Ganga bridge parallel to the Digha-Sonepur rail-road bridge, while clarifying that the writ petitioners can pursue their title claims in the pending civil suit but will not receive interim protection halting the project. The Court reiterated that if the petitioners succeed in the title suit, they will be entitled only to compensation.


Facts

The petitioners claimed to have inherited land at Digha Ghat, asserting that it was settled with their ancestors by the erstwhile Province of Bihar. They filed a writ petition in 2014 seeking protection of possession or, alternatively, a direction to the State to acquire the land and pay compensation, alleging interference due to the State’s and Railways’ Ganga bridge construction project. A learned Single Judge granted interim status quo protection in 2015, relying on a 2014 judgment which recognised the settlement’s validity. However, that judgment was overturned in 2015 by a Division Bench, which held that the claim could only be adjudicated through a civil suit, and the State could proceed with its project. Despite the State’s application to vacate the status quo, the interim order persisted, delaying the bridge project estimated at Rs. 2221.47 crores. The present appeal was filed by the State seeking vacation of the interim order and permission to continue the bridge construction.


Issues

  • Whether the petitioners were entitled to continued interim protection despite the Division Bench’s ruling requiring adjudication through a civil suit.
  • Whether the State could proceed with the construction of the six-lane Ganga bridge at Digha during the pendency of the petitioners’ title suit.
  • The impact of public interest and large-scale infrastructure development on interim relief in private land disputes.

Petitioner’s Arguments

The petitioners argued that they were in possession of the disputed land, which was settled with their ancestors, and that the State and Railways should be restrained from interfering with their possession until the matter was fully adjudicated. They relied on the 2014 Single Judge’s judgment affirming the validity of their settlement, seeking either protection of their possession or direction to the State for acquisition and payment of compensation to avoid dispossession without due process.


Respondent’s Arguments

The State argued that the 2014 judgment relied upon by the petitioners was overturned by a Division Bench in 2015, which held that the issue of settlement validity required adjudication in a civil suit. The State emphasised that the interim status quo order hindered the progress of the vital six-lane Ganga bridge project, which was of significant public interest, and that the petitioners’ rights could be decided in the civil suit without halting the project.


Analysis of the Law

The Court analysed the legal position that land disputes involving title and settlement claims must be adjudicated through civil suits rather than writ proceedings. It reiterated that interim protection in such cases cannot be extended indefinitely, particularly when public projects of substantial importance and investment are at stake. The Court acknowledged the petitioners’ right to pursue their claims in the civil suit but clarified that such claims do not entitle them to halt public infrastructure projects without a clear adjudication of rights.


Precedent Analysis

The Court primarily relied on its own Division Bench decision in LPA No. 34 of 2015 (judgment dated 15 December 2015), which had overturned the earlier Single Judge decision relied upon by the petitioners, holding that the validity of settlement claims over government land must be decided through a civil suit. The precedent also clarified that the State could proceed with public projects while claimants could only seek compensation if they later succeeded in establishing title.


Court’s Reasoning

The Court reasoned that the continuation of the interim status quo, despite the clear ruling of the Division Bench requiring civil adjudication, unjustifiably hindered the State’s public project, which involved significant investment and a strict timeline for completion. It observed that maintaining the status quo would indefinitely stall the construction of the Ganga bridge, impacting public interest. It further clarified that the petitioners’ remedy lay in pursuing the pending title suit before the Sub-Judge, and if successful, they could claim compensation, but this did not entitle them to obstruct the ongoing project.


Conclusion

The Patna High Court disposed of the Letters Patent Appeal and the connected writ petition by:

  • Allowing the State to continue construction of the six-lane Ganga bridge at Digha without any interim injunction.
  • Granting the petitioners liberty to pursue their pending title suit to establish their claim.
  • Clarifying that if the petitioners succeed in the suit, they will be entitled to compensation, not restoration of possession.

The interim status quo was effectively lifted to facilitate the continuation of the public project while preserving the petitioners’ right to claim compensation based on the civil suit’s outcome.


Implications

  • Public infrastructure projects will not be stalled due to private land disputes unless title is adjudicated in favour of claimants.
  • Establishes that civil suits are the appropriate forum for determining complex land title issues, not writ petitions.
  • Balances public interest in large infrastructure projects with private rights by preserving compensation claims while allowing projects to proceed.

Short Notes on Referred Cases

LPA No. 34 of 2015 (Patna High Court, 15 December 2015): Held that settlement disputes over Khasmahal lands should be resolved through civil suits, not writ petitions, and that public projects should not be obstructed due to interim orders in such disputes. This precedent formed the basis for lifting the interim status quo in the present case, aligning judicial policy in balancing public interest with private rights.


FAQs

1. Can claimants stop public projects while claiming land rights?
No, the High Court clarified that pending title suits do not entitle claimants to halt public projects; they can claim compensation later if they succeed.

2. How should land disputes with government land be resolved in Bihar?
Such disputes should be resolved through civil suits, not through writ petitions, particularly where the land is claimed as settled government land.

3. What happens if the petitioners win the title suit later?
If the petitioners succeed in the title suit, they will be entitled to compensation for the land, but the public project will not be reversed.

Also Read: Patna High Court Quashes Cheating and Forgery Case Against Bank Manager Alleged of Sanctioning Fraudulent Loan Using Joint Family Property Without Consent, Emphasises Settlement and Lack of Prima Facie Case

Comments

No comments yet. Why don’t you start the discussion?

Leave a Reply

Your email address will not be published. Required fields are marked *