Court’s Decision: The Supreme Court reviewed its previous judgment regarding a dispute over the enforcement of a specific performance contract and ruled in favor of the petitioner by recalling its earlier decision dated August 25, 2022. The Court found errors in interpreting critical contract clauses and ruled that the petition was within the limitation period. The case was reverted to the High Court’s decision, which partially decreed specific performance based on the consideration paid by the petitioner.

Facts: The case originated from an agreement executed between the vendors and the petitioner in 1997, in which the petitioner sought specific performance for the transfer of land after fulfilling part of the consideration. The vendors claimed they had not received the full payment and thus refused to execute the sale deed, leading the petitioner to file a suit for specific performance.

The trial court dismissed the petitioner’s suit, concluding that the petitioner was not entitled to a decree for specific performance due to alleged lack of possession and non-fulfillment of contract terms, including timely payment. The High Court, upon appeal, partly allowed the suit, directing the transfer of land proportionate to the amount paid by the petitioner.

Issues:

  1. Whether the suit filed by the petitioner was barred by limitation.
  2. Whether the petitioner was entitled to specific performance under the agreement terms.

Petitioner’s Arguments: The petitioner argued that the Supreme Court’s previous judgment had errors in interpreting critical contract clauses. It misinterpreted the timeline and obligations outlined in the clauses, leading to an incorrect finding on the limitation period. The petitioner contended that they were ready and willing to perform the contract and had already fulfilled 90% of the consideration.

Respondent’s Arguments: The respondents argued against exercising review jurisdiction, asserting that the contract’s performance was contingent upon timely payment, which the petitioner failed to fulfill within the stipulated period. They maintained that the contract was nullified by the petitioner’s breach of essential conditions and delayed legal action.

Analysis of the Law: The Court examined the grounds for review under Order 47 Rule 1 of the Civil Procedure Code, which include error apparent on the face of the record. The Court noted that while the specific performance of contracts is generally discretionary, Section 16(c) of the Specific Relief Act mandates that the party seeking enforcement must demonstrate readiness and willingness to perform their contractual obligations.

Precedent Analysis: The Court referenced Chand Rani v. Kamal Rani, which established that “time is not presumed to be of essence” in immovable property contracts unless explicitly stated. The Court also examined Saradamani Kandappan v. Rajalakshmi, which requires the courts to evaluate whether contract time limits should be treated strictly based on surrounding circumstances.

Court’s Reasoning: The Court found that its previous interpretation of certain clauses was flawed. Specifically, it overlooked the cancellation provision in Clause 3, which imposed consequences for non-performance by either party, not solely the petitioner. Additionally, Clause 21 was misinterpreted as binding the petitioner to an earlier agreement, leading to an erroneous conclusion that the time was of the essence in the contract. The Court concluded that the petitioner’s suit was filed within the permissible limitation period and that the petitioner was indeed ready and willing to perform the contract.

Conclusion: The Supreme Court reversed its previous decision, stating that both the findings on limitation and specific performance were based on errors. The High Court’s judgment, which had decreed specific performance to the extent of the consideration already paid, was reinstated.

Implications: This ruling emphasizes the importance of accurately interpreting contract terms, especially in specific performance cases where immovable property is involved. It reinforces that unless explicitly stated, time is generally not of essence in such contracts, and statutory presumption supports the view that immovable property transfers warrant specific performance over monetary compensation.