interim protection

Sikkim High Court Directs Continuation of Interim Protection for JRA Infrastructure Against Coercive Steps by Union of India While Dispute Redressal Committee Proceedings Continue, Declining Immediate Arbitration Reference Pending Pre-Arbitration Process

Share this article

Court’s Decision

The Sikkim High Court disposed of two arbitration petitions filed by JRA Infrastructure, one under Section 9 and the other under Section 11 of the Arbitration and Conciliation Act, 1996, with a direction that the ad-interim order restraining the Executive Engineer, CPWD, from taking coercive steps against JRA Infrastructure will continue until the Dispute Redressal Committee (DRC) concludes its proceedings. The Court declined to proceed with arbitration under Section 11 since the parties had agreed to a pre-arbitration DRC mechanism, currently underway, and held that the interim order would continue to govern the parties until the DRC decides the disputes.


Facts

JRA Infrastructure filed two arbitration petitions against the Union of India, one seeking interim protection under Section 9 and the other seeking appointment of an arbitrator under Section 11 of the Arbitration Act in relation to disputes arising from a government project under the CPWD Border Road Project, North Sikkim. An ad-interim injunction was granted on 23 April 2025 restraining the Executive Engineer from taking coercive steps against JRA Infrastructure without court permission. Later, on 14 May 2025, the Court clarified that it had not restrained the respondent from opening tenders, and the CPWD could proceed with tender opening despite the injunction. Meanwhile, the disputes were referred to the DRC as a pre-condition to arbitration per the contract, and the DRC fixed the first hearing for 6 June 2025.


Issues

  1. Whether the arbitration petitions could be decided when the parties had agreed upon a pre-arbitration Dispute Redressal Committee mechanism that was still pending.
  2. Whether the interim protection granted to JRA Infrastructure under Section 9 should continue while the DRC proceedings were ongoing.

Petitioner’s Arguments

JRA Infrastructure argued that it had disputes with the Union of India that needed urgent adjudication under the arbitration clause and sought interim protection to prevent coercive actions by the CPWD which would adversely affect its rights. It urged the Court to continue interim protection pending resolution of disputes and argued that the matter should proceed towards arbitration to avoid indefinite delay despite the DRC mechanism.


Respondent’s Arguments

The Union of India argued that as per the contract, parties had agreed to a pre-arbitration DRC mechanism, which had not been exhausted, making the arbitration petition under Section 11 premature. The Union also contended that the DRC process was actively underway, and there was no justification to bypass it, requesting dismissal of the arbitration petitions until the DRC proceedings concluded.


Analysis of the Law

The Court analysed that under the Arbitration and Conciliation Act and the contract between the parties, a pre-arbitration DRC mechanism was a mandatory pre-condition to invoking arbitration, and parties must first exhaust this process before proceeding with arbitration. The Court noted that while interim measures under Section 9 could be entertained in appropriate cases even prior to arbitration, proceeding with a Section 11 application for arbitrator appointment would be premature until the DRC procedure concluded.


Precedent Analysis

The judgment reflected consistent principles under:

  • Arbitration and Conciliation Act, 1996: Interim measures can be granted under Section 9 to protect rights pending arbitration.
  • Established arbitration precedents requiring mandatory pre-arbitration dispute resolution steps to be completed before arbitration reference.
  • The judgment noted that references to multiple judgments in the Chief Engineer’s letter regarding the DRC mechanism were unnecessary without discussing the facts but did not affect the legal requirement to exhaust the DRC process.

Court’s Reasoning

The Court held that the parties had a clear contractual obligation to first exhaust the DRC process before seeking arbitration. Since the DRC had fixed its first hearing for 6 June 2025 and the process was ongoing, the arbitration petitions under Section 11 could not proceed at this stage. However, recognising the need to protect JRA Infrastructure’s interests pending resolution, the Court decided that the interim protection granted under the Section 9 petition would continue to operate until the DRC proceedings concluded.


Conclusion

The Sikkim High Court disposed of the two arbitration petitions, directing that the interim order dated 23 April 2025 restraining the Executive Engineer from taking coercive steps against JRA Infrastructure will continue until the DRC concludes its proceedings. The Court held that arbitration proceedings under Section 11 were premature until the DRC process concluded, thereby maintaining the balance between contractual procedure and interim protection.


Implications

  • Reinforces the requirement to exhaust pre-arbitration dispute resolution mechanisms (DRC) before seeking arbitration.
  • Confirms courts can continue interim protection under Section 9 while pre-arbitration processes are pending.
  • Establishes that unnecessary legal references in administrative communications should be avoided for clarity.

Brief on Cases Referred

The Chief Engineer’s letter referred to multiple judgments to justify the DRC requirement, but the Court found referencing judgments without factual context inappropriate, reaffirming that clear communication is preferable in contractual dispute processes. No specific case names were central to the ruling, but the Court applied general arbitration principles regarding pre-arbitration dispute resolution and interim protection.


FAQs

1. Can a party seek arbitration before completing pre-arbitration DRC procedures?
No, parties are required to exhaust agreed pre-arbitration mechanisms before seeking arbitration.

2. Can interim protection under Section 9 be granted while DRC proceedings are pending?
Yes, courts can grant and continue interim protection to safeguard parties’ rights until pre-arbitration processes conclude.

3. What happens if the DRC process is ongoing but the party seeks arbitration?
The arbitration petition will be premature and can be deferred until the DRC process concludes, while interim measures may continue.

Also Read: Bombay High Court Quashes Maharashtra Revenue Tribunal Order Overturning Concurrent Findings of Authorities, Upholds Tenant’s Deemed Purchase Rights under Land Tenancy Law, Emphasising Limits of Revisional Jurisdiction under Section 76 of Tenancy Act

Comments

No comments yet. Why don’t you start the discussion?

Leave a Reply

Your email address will not be published. Required fields are marked *