News

Delhi High Court Upholds Arbitral Award Quashing DoT’s ₹8.55 Crore Demand Against Sterlite; Finds No Proof It Provided Unlicensed End-to-End Bandwidth Services

11 min read

Delhi High Court Upholds Award Against DoT’s ₹8.55 Crore Demand; Finds No Proven IP-I Violation, Actual Loss or Basis for Pan-India Recovery

Facts

The Union of India through the Department of Telecommunications (DoT) filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award dated 17 May 2023 in favour of Sterlite Technologies Limited (STL).

Sterlite, which designs and integrates digital networks and provides technological solutions, held an Infrastructure Provider Category-I (IP-I) Registration Certificate, permitting it to provide passive telecom infrastructure.

Sterlite’s wholly owned subsidiary, Sterlite Networks Limited, subsequently renamed Speedon Network Limited (SNL), entered into a Master Service Agreement dated 20 January 2012 with Citycom Networks Private Limited for providing access infrastructure. Sterlite entered into another MSA dated 25 May 2012 with Microscan Computers Private Limited (MCPL).

DoT alleged that the payment structure under these agreements was based upon subscriber base and revenue sharing rather than lease rentals for passive infrastructure and therefore Sterlite was effectively operating as a Telecom Service Provider without the requisite licence.

On 26 February 2015, DoT inspected Sterlite’s Pune premises. The inspection report concluded that Sterlite was allegedly selling bandwidth beyond the scope of its IP-I registration, managing and operating equipment through SNL, and had thereby evaded more than ₹2.5 crore in government revenue towards National Long Distance licence entry and annual licence fees.

Following correspondence and exchange of information, DoT issued a show-cause notice on 30 July 2018.

Thereafter, on 24 August 2020, DoT raised a demand of ₹8,55,75,236 against Sterlite. Sterlite’s request for reconsideration was rejected on 21 October 2020.

Sterlite invoked arbitration pursuant to the dispute resolution clause in its IP-I Registration Certificate. A sole arbitrator was appointed by the Delhi High Court on 23 April 2021.

The arbitrator ultimately held DoT’s demand to be illegal, arbitrary, irrational and unjustified. DoT therefore challenged the award under Section 34.


Issues

The principal issues before the High Court were:

  1. Whether Sterlite had exceeded the scope of its IP-I Registration Certificate by owning or operating active telecom infrastructure;
  2. Whether Sterlite was effectively providing end-to-end bandwidth services without possessing the requisite telecom licence;
  3. Whether Sterlite and its wholly owned subsidiary SNL could be treated as a single entity for determining regulatory liability;
  4. Whether the payment mechanism under the MSAs demonstrated that Sterlite was charging for bandwidth rather than merely providing passive infrastructure;
  5. Whether DoT could impose damages for breach of the IP-I Registration Certificate without any statutory or contractual provision authorising such demand;
  6. Whether actual loss had been pleaded and proved for claiming damages under Section 73 of the Contract Act;
  7. Whether DoT could raise a pan-India demand based solely upon an inspection conducted at Sterlite’s Pune premises; and
  8. Whether the arbitral award suffered from perversity, patent illegality or any other defect warranting interference under Section 34 of the Arbitration Act.

Petitioner’s Arguments

DoT argued that the arbitrator had failed to properly appreciate the evidence demonstrating that Sterlite was operating beyond the permissible scope of an IP-I registrant.

It relied particularly upon a letter dated 6 June 2015 from SNL, which according to DoT amounted to an admission that the relevant equipment belonged to Sterlite.

DoT argued that neither Sterlite nor SNL possessed the requisite licence at the relevant time to own or operate active telecom equipment.

It further contended that Sterlite was permitted only to establish passive infrastructure, whereas the MSAs and billing arrangements demonstrated provision of end-to-end bandwidth services.

According to DoT, billing was linked to bandwidth utilisation rather than dark fibre infrastructure, indicating that Sterlite was effectively operating as a Telecom Service Provider.

DoT also alleged that SNL was merely being used as a facade, while Sterlite was the real beneficiary and actual service provider.

DoT further argued that the arbitrator had wrongly held that damages were unrecoverable in the absence of an express provision in the IP-I Registration Certificate.

According to DoT, damages for breach of the registration conditions constituted an inherent right and did not depend upon an express contractual clause.


Respondent’s Arguments

Sterlite defended the arbitral award and contended that there was no evidence establishing that it owned the active equipment or provided end-to-end bandwidth services.

It argued that broadband services and bandwidth were actually provided by the licensed Telecom Service Providers, including Citycom.

Sterlite relied upon the contractual allocation of responsibilities under the MSAs to show that its role was confined to passive infrastructure, while active equipment and subscriber services remained the responsibility of the TSPs.

Sterlite also relied upon the Supreme Court judgment in Vodafone International Holdings B.V. v. Union of India, (2012) 9 SCC 407, to argue that a holding company and its subsidiary are separate legal entities.

It further argued that:

  • a pan-India demand could not legally be raised on the basis of one inspection conducted at Pune; and
  • damages under Section 73 of the Contract Act could not be imposed in the manner adopted by DoT.

Analysis of the Law

1. Regulatory Scope of an IP-I Registrant

The Court examined the regulatory distinction between an IP-I registrant and a licensed Telecom Service Provider.

Under Section 4 of the Indian Telegraph Act, 1885 and Clause 2.0 of Sterlite’s Registration Certificate, telegraph services including end-to-end bandwidth could only be provided by licensed entities.

IP-I registrants were restricted to establishing and leasing passive telecom infrastructure to Telecom Service Providers.

The central factual question was therefore whether Sterlite had crossed this boundary.

2. No Proof Sterlite Owned Active Equipment

The arbitrator had extensively examined the equipment found during the Pune inspection, correspondence exchanged thereafter, and the MSAs.

Sterlite had denied ownership of active equipment and provided lists identifying the relevant TSPs and equipment.

The contractual documents also showed that the Telecom Service Providers bore responsibility for backhaul equipment and bandwidth required for providing services to subscribers.

The High Court found no reason to disturb the arbitrator’s conclusion that Sterlite did not own the active equipment and provided only passive access infrastructure.

DoT’s reliance upon SNL’s letter dated 6 June 2015 was rejected because the letter merely stated that equipment had been leased to various TSPs; it did not contain an admission that Sterlite owned that equipment.

3. No Proof of End-to-End Bandwidth Services

The arbitrator had separately examined whether Sterlite actually provided end-to-end bandwidth.

The charging mechanisms, consideration clauses and payment provisions of the MSAs were examined in detail.

The arbitrator found that monthly recurring charges were not calculated according to bandwidth capacity used by end subscribers.

Further, the Citycom MSA demonstrated that Sterlite itself depended upon Citycom for bandwidth required for maintenance services.

The Court also noted that the MSAs allocated passive infrastructure responsibilities to Sterlite, while active infrastructure and subscriber services remained with the TSP.

DoT did not dispute that passive infrastructure services could lawfully be provided by Sterlite under its IP-I registration.

The High Court therefore held that the arbitrator’s factual finding suffered from no legal or factual error warranting interference under Section 34.

4. Sterlite and SNL Were Separate Legal Entities

DoT attempted to argue that SNL was effectively a facade for Sterlite.

The Court rejected this contention.

SNL had separately received an IP-I Registration Certificate on 28 March 2014 and subsequently obtained a Unified Licence on 26 March 2018.

The fact that DoT itself had granted separate registrations to the two entities supported their distinct corporate existence.

The Court also noted that DoT had not even pleaded in its statement of defence before the arbitrator that Sterlite and SNL constituted a single legal entity; that contention was introduced only during arguments.

Further, an NCLT-approved scheme of arrangement expressly recognised SNL as Sterlite’s wholly owned subsidiary, reinforcing their distinct legal status.

5. Government Demand Required Statutory Backing

A particularly significant aspect of the judgment concerned DoT’s authority to impose the demand.

The Court noted that there was no statutory provision under the Telegraph Act and no clause in the IP-I Registration Certificate authorising the particular damages demanded for breach of the registration conditions.

The Court expressly observed:

“The demand raised by a statutory authority requires a statutory backing.”

This materially weakened DoT’s case.

6. Section 73 Contract Act Required Proof of Loss

The arbitrator relied upon decisions of the Telecom Disputes Settlement and Appellate Tribunal in Oil India Ltd. v. Union of India and Viom Network Ltd. v. S Tel Private Ltd. & Ors.

Although the High Court observed that TDSAT decisions were not binding upon it, they supported the plausibility of the arbitrator’s view.

The Court further explained that damages under Section 73 of the Contract Act require satisfaction of two essential conditions:

  1. breach of the contractual obligation; and
  2. actual loss or damage, or proof that actual loss is incapable of being established.

DoT had neither properly pleaded nor proved actual loss suffered because of the alleged violation.

The second essential requirement for damages under Section 73 was therefore absent.

7. Pan-India Demand Based on One Pune Inspection Was Unsustainable

DoT had inspected only Sterlite’s premises at Pune.

No corresponding inspection had been carried out in any other city.

Nevertheless, the authorities presumed that similar activity was occurring elsewhere and generated a nationwide demand.

The arbitrator described this approach as “pernicious,” and the High Court agreed that the pan-India demand lacked an adequate factual basis.


Precedent Analysis

The High Court relied upon recent Supreme Court authorities emphasising the extremely restricted scope of judicial interference with arbitral awards under Section 34.

Prakash Atlanta (JV) v. National Highways Authority of India, 2026 INSC 76

The Supreme Court held that where the arbitrator adopts a possible and plausible interpretation, the Court cannot substitute another interpretation merely because an alternative view is possible.

Interpretation of contractual terms primarily belongs to the arbitral tribunal, and interference is justified only where the interpretation is one that no fair-minded or reasonable person could reach.

Ramesh Kumar Jain v. Bharat Aluminium Company Limited (BALCO), 2025 INSC 1457

The Supreme Court reiterated that Section 34 confers only a narrow supervisory jurisdiction.

A Section 34 Court does not sit in appeal over the arbitral award and cannot ordinarily examine the correctness or reasonableness of findings merely because another view is possible.

Consolidated Construction Consortium Ltd. v. Software Technology Parks of India, (2025) 7 SCC 757

The Supreme Court held that Section 34 is not an appellate provision.

Courts cannot re-appraise evidence and substitute their own conclusions merely because the award may contain an error of law. If two views are possible, the arbitrator’s view must ordinarily prevail.

SEPCO Electric Power Construction Corporation v. GMR Kamalanga Energy Ltd., 2025 INSC 1171

The Supreme Court reiterated that even where an arbitrator’s factual or legal reasoning may be faulty, courts should ordinarily refrain from interfering unless the error falls within the narrow statutory parameters governing challenges to arbitral awards.

Vodafone International Holdings B.V. v. Union of India, (2012) 9 SCC 407

Sterlite relied upon Vodafone International Holdings for the proposition that a holding company and subsidiary remain separate legal entities.

This principle supported Sterlite’s resistance to DoT’s attempt to effectively treat Sterlite and SNL as one entity merely because SNL was its wholly owned subsidiary.


Court’s Reasoning

The High Court emphasised that its jurisdiction under Section 34 was not equivalent to a first appeal.

It could not undertake a fresh evaluation of the contractual documents, correspondence and technical evidence merely because DoT proposed a different interpretation.

The arbitrator had examined the controversy from four distinct perspectives:

  • ownership of active equipment;
  • whether Sterlite provided end-to-end bandwidth;
  • separate legal personality of Sterlite and SNL; and
  • legality of DoT’s demand.

The findings were based upon the Registration Certificate, MSAs, correspondence, inspection report, contractual allocation of responsibilities and applicable regulatory framework.

The Court found the arbitrator’s interpretation to be a plausible view supported by the record.

There was neither perversity nor a legal or factual error of the nature contemplated by Section 34.

Consequently, even if DoT considered another interpretation preferable, that could not justify judicial substitution of the arbitrator’s findings.

The Court ultimately held that the arbitrator had given detailed reasons for setting aside DoT’s demand and that those findings fell squarely within the permissible decisional domain of the arbitral tribunal.

Conclusion

The Delhi High Court dismissed the Union of India/DoT’s Section 34 petition and refused to interfere with the arbitral award in favour of Sterlite Technologies Limited.

The Court upheld the arbitrator’s findings that:

  • Sterlite was not proved to own the relevant active telecom equipment;
  • Sterlite was not proved to have provided unauthorised end-to-end bandwidth services;
  • its activities under the relevant MSAs were consistent with provision of passive infrastructure;
  • Sterlite and SNL were separate legal entities;
  • DoT lacked demonstrated statutory or contractual backing for the damages demanded;
  • actual loss necessary for damages under Section 73 of the Contract Act was not pleaded or proved;
  • a pan-India demand based only upon a Pune inspection lacked a proper factual foundation; and
  • the arbitrator’s view was plausible and disclosed no perversity warranting interference under Section 34.

Accordingly, the ₹8,55,75,236 demand remained set aside, and DoT’s challenge failed.

Case Details

Case: Union of India, Through Secretary, Department of Telecommunications, Ministry of Communications, Government of India v. Sterlite Technologies Limited
Court: High Court of Delhi at New Delhi
Case Number: O.M.P. (COMM) 395/2023
Judge: Justice Avneesh Jhingan
Date: 12 August 2026
Result: Section 34 petition dismissed; arbitral award setting aside DoT’s ₹8.55 crore demand against Sterlite Technologies upheld.

Read also: Delhi High Court Upholds Rejection of Suit Challenging 2016 Sale Deed Registered in 2018; Finds Seller Admitted Execution and Disclosed No Cause of Action

Leave a Reply

Your email address will not be published. Required fields are marked *